COMPARISON GUIDE

Retaining-Wall Base Stone vs Drainage Stone

A segmental retaining wall can use aggregate below the first block and gravel fill behind the wall, but those zones have different jobs. Ordering one generic pile of stone for both can conflict with the wall-system specification and drainage design.

By Plan My Materials Editorial Team

Keep each wall material in its assigned zone

The wall manufacturer, designer, site engineer, and geotechnical recommendations control the final materials and dimensions.
Wall zonePrimary jobPlanning check
Leveling pad below the unitsProvides a firm, level bearing surface for the first courseApproved compactable granular material or concrete option, excavation, width, thickness, elevation, and compaction
Gravel fill directly behind and within units where specifiedLimits fines migration, reduces face-compaction stress, and helps incidental water reach the drainClean crushed stone or granular fill gradation, width, height, placement, and compatibility with the block system
Drain pipeCollects and conveys water to a safe outletPipe type, diameter, elevation, slope, outlet, cleanout, and site-drainage connection
Filter geotextileSeparates soils where needed while permitting designed water movementFilter criteria, overlap, placement, and whether the designer requires wrapping the gravel or pipe
Reinforced or retained backfillProvides the engineered soil mass behind the faceSoil classification, gradation, moisture, lift thickness, compaction, geogrid, and drainage details

Why base aggregate and gravel fill are not the same line item

CMHA sample specifications describe a compacted granular leveling pad below the wall units and a separately specified gravel fill behind them. The leveling pad supports alignment and bearing. The gravel-fill zone is selected and placed for face construction, filtering, and incidental drainage functions.

CMHA also cautions that the gravel fill and drain pipe are not the primary site-drainage path. Surface water should be directed away, and groundwater, outlets, collection systems, and erosion control require site-specific design. Simply adding more stone behind the wall does not replace that work.

Names such as road base, crusher run, three-quarter-inch stone, drain rock, clear stone, and number 57 stone are regional and do not prove compliance. Request the gradation and source, then compare them with the exact wall-system specification.

Information to collect before ordering stone

  • Wall manufacturer, block family, approved installation manual, design drawings, and local permit requirements.
  • Finished wall length, exposed height, buried courses, steps, curves, corners, and separate wall sections.
  • Leveling-pad material, width, compacted thickness, extension beyond the unit, and compaction requirement.
  • Gravel-fill gradation, width, full placed height, unit-core fill requirement, and separation from native soil.
  • Drain-pipe type, diameter, route, slope, outlet elevation, cleanouts, and protection from clogging or freezing.
  • Supplier density, moisture, truck capacity, minimum order, delivery access, staged placement, and project-appropriate allowance.

WORKED EXAMPLE

Calculate the two aggregate zones separately

This hypothetical 20-foot wall uses assumed dimensions only to show the arithmetic. The wall design must supply the real dimensions and materials.

Assumed leveling pad
20 ft × 2 ft wide × 0.5 ft thick = 20 cu ft
Leveling-pad cubic yards
20 ÷ 27 = 0.74 cu yd before allowance and supplier rounding
Assumed gravel-fill zone
20 ft × 1 ft wide × 3 ft placed height = 60 cu ft
Gravel-fill cubic yards
60 ÷ 27 = 2.22 cu yd before deductions, allowance, and supplier rounding
Purchase plan
Keep 0.74 yd³ of approved base material separate from 2.22 yd³ of approved gravel fill
Do not use this example's dimensions as a wall detail. Account for actual cross-sections, unit cores, pipe displacement if required, steps, corners, compaction, material density, and delivery increments.

Sources and further reading

  1. Segmental Retaining Wall DesignConcrete Masonry & Hardscapes Association · Accessed November 14, 2026

    Site-specific drainage responsibilities, gravel-fill functions, incidental-water limitation, drain pipe, and wall-designer scope.

  2. Segmental Retaining Wall Sample SpecificationsConcrete Masonry & Hardscapes Association · Accessed November 14, 2026

    Separate leveling-pad, gravel-fill, reinforced-backfill, geotextile, pipe, placement, and foundation requirements.